Current Status
Team should update this status report every sprint.
Gitlab Board and issues
Status of sprint 06 Date 12.4.2024
What has been achieved
- Demo is almost ready for demo day
- Powerpoint presentation for demo day is ready
Do we have a problems/challenges?
- Nothing special
Next steps
- Get ready to present our demo
Status of sprint 05 Date 5.4.2024
What has been achieved
- FEA201 ready for testing
- Updated roadmap
- Demo in good shape for demo day
Do we have a problems/challenges?
- Not really
Next steps
- Prepare demo ready for the demo day
- Continue working on features
Status of sprint 04 Date 22.3.2024
What has been achieved
- Finished implementation of Improve dark mode colors (FEA106)
- Logos have been changed to GUI Guerillas and JAMK (FEA112)
- Successfully finished Export Data to csv (FEA201)
- Successfully made Control access to the server (FEA407)
- Reviewed sprint 04 issues
Do we have a problems/challenges?
- Our team and JAMK logo colors changed while turning dark mode on
- Not much!
Next steps
- Continue working on features
- Start planning sprint 05
Status of sprint 04 Date 11.3.2024
What has been achieved
- We have got closed lot of issues
- Updated documents
Do we have a problems/challenges?
- Not much!
Next steps
- Starting to working with chosen features!
Status of sprint 02 Date 23.2.2024
What has been achieved
- Updated project plan
- Created preliminary road map in gitlab
- Updated features
- Created test cases for features
- Updated team website
- Updated communication plan
- Updated current status
Do we have a problems/challenges?
- Getting to know what to write in the documentation takes some learning.
- Creating a better team working environment.
Next steps
- Proceed to Sprint 03
Status of sprint 02 Date 19.2.2024
What has been achieved
- Started working with the sprint 02 issues.
Do we have a problems/challenges?
- Not really. Everything is going fine at the moment.
Next steps
- Continue writing documents and working with issues.
Status of sprint 01 Date 5.2.2024
What has been achieved
- Started working with the sprint 01 issues.
- Getting Tukko running
- Decided what possible features we might want in Tukko.
Do we have a problems/challenges?
- We had problems getting docker to work.
Next steps
- Continue writing documents.
Status of sprint 00 Date 26.1.2024
What has been achieved
- Introductions are done and we came up with a name for the team.
- Familiarized ourselves with our customer and the product we will work on.
- We assigned team roles and also assigned work for everyone.
- Created issues and milestones.
- We have started working on our team pages and managing issue board.
Do we have a problems/challenges?
- In first two lessons had slight lack of understanding of the whole course but now things are getting under control.
- No bigger problems.
Next steps
- Working with the issue board management and read more about Tukko. Also start think about what we want to offer to customer. Keep working!